Rattlesnake Bridge work
April 21, 2019

On Friday, April 19th, Bolton Trails work party comprised of Jeffery Bryan, Larry Kunz, Andrew schaubhut and Bob Reimer met at Rattlesnake trail to build a new bridge. Rattlesnake trail needed a bridge at the great brook crossing near environment pools.
Bob reviewed the existing arrangement that was being used a bridge was extremely slippery and was not safe to cross the brook. He arranged rocks ahead of their planned work day for the new bridge. Bob also came up with a rough design for the bridge. They hiked to the trail with the necessary equipment and supply to build the bridge.
Whole work was done in one day. Bridge is 36 feet long. Now everyone can enjoy brook crossing safely. Thank you to our amazing group of trail warriors! Enjoy pictures. Bridge looks great.
old bridge site analysis new bridge from side from distance detailed view strong base bridge close up lay out of bridge new shiny bridge laying it out brook bridge base view of bridge Bridge and crew check it out test passed bridge in place tricky measurements brook in spring crew at work prepare site work in progress brook drill work drill done laying it put setting the bridge hmm, looks good so far yes, this will work detailed work Drill is done! based looks good drilling.. the brook water level side brook